Case Study

Façade retention project for Premier Jewellery Retailer

£7 Million Value
60 Weeks Duration
Old Bond Street Location

The Brief:

This project required major facade retention, which involved the keeping of the listed facade, top floor and roof and the demolition of the entire structure down to basement level and the reconstruction of the new building.

The Project Involved:

  • Structure demolition of 5 floors
  • New structure including new slabs and external walls
  • Refurbishment of existing facade including all windows
  • Installation of new vault
  • Installation of new glass feature elevator
  • Structural feature staircase wrapping glass shaft
  • Mechanical and electrical installation
  • Installation of a mist fire suppression system
  • Feature timber cladding to staircase
  • Shop fit-out

Related Case Study

Monica Vinader

Fit out and installation of new staircase within Shopping Centre.

Read this case study

Related Case Study

Louis Vuitton Selfridges

Complete fit out within a trading store including the installation of revolving feature glass elevator.

Read this case study

Related Case Study

Internationally Renowned Fashion Retailers – Global Flagship Store and Offices

This project involved the structural remodeling and fitting out of a high-end fashion boutique and 3000m2 of Office space.

Read this case study
 

Ready to talk?

Get in touch using the channels below or click the ‘Request call back’ button and we’ll give you a call at your convenience.

Close

Request a Call Back

Please leave your details below and we’ll get back to you within 24 hours.

Error: Contact form not found.